1st Floor Framing
More 1st Floor Framing: Got the electrical panel installed and started the 14' tall walls. Also got one corner of the house logs cut and...


Septic Tank & Drain Field Installation
UPDATE 4/15/16 Backfill Drone Flight: TIme Lapse Video Installed the new septic tank and drain field. Time Lapse Video:


Drone Shots
Flights on the evening of 4/6/16 after slab was poured. A little windy so I didn't take it up to high. Flight on 3/12/16 after backfill...


Interior Concrete Slab
UPDATE: 4/6/16 Slab poured today! YAHOOOOO!! Time Lapse Videos: UPDATE: 3/30/16 Installation of rebar. Time Lapse Video Of Rebar...


Lumber
Lumber for the first floor was delivered on Friday April 1st. Waiting on the slab to be poured. Didn't have much to do so I graded...


Radiant Heat System
A VERY BUSY AND PRODUCTIVE WEEKEND!! Starting With A Long Day On Friday..... Vapor Barrier and Foam Board Installation. 6 Mil. Vapor...


Sleeves, Stem Wall Insulation, & Backfill
Update: March 18, 2016. Final Graded and Compaction of 1" Crushed Gravel. Saturday March 12, 2016. Backfilled for slab. Still need to...


Stem Walls
Update: Time Lapse Video of form stripping and first load of gravel. Started to bring in the backfill gravel on Monday night. Using 1"...


Water Supply Line
Trenched the new water line, installed the new pipe, and tracer wire yesterday evening. Passed the inspection today and installed the...


Siding Examples
Built some mockups of some siding options. I still need to stain them. Option 1 - Log Veneer Option 2 - 12" Board with 3" Batten Option...